Project Date

June & July 2025

Project Goals

To eliminate OH&S risks associated with manual sampling, particularly the hazard of having personnel in the truck traffic area. To improve consistency of grain samples and achieve a more representative sample of the load.

Project Description

Following consultation with our client, we supplied, installed and commissioned 1 x Samplex CS90 Bulk Grain Sampler at Mauri’s Moorooka site. Custom fabrication of the pipework was required due to the location of the sampler in relation to the sample hut. Being in a flood prone area, elevation of the equipment was also important.

Outcome

Personnel are no longer required in the truck traffic area and the CS90 ensures sampling is no longer restricted to the top layer of the load. The custom pipework ensures steady flow of product, and strategic installation of the equipment at height minimizes risk during flood events.

Financial or Operational Impact

  • OH&S risks associated with personnel in the truck traffic area eliminated
  • A more consistent and representative sample of grain is now achieved
  • Custom Fabrication ensures adequate flow of product through pipework is achieved
  • Installation at height minimizes the impact of potential flooding

Client Feedback

“I first contacted Andrew at McCabe Engineering Services in February of 2023 about an extensive upgrade at our Moorooka plant. Throughout the entire process, from initial contact through to planning, installing and commissioning, I have found Andrew to be professional and responsive. He delivers first-class products and service to match.”

Petrus Swart
Engineering Manager
Mauri